File #: 23-0732    Version: 1 Name:
Type: Resolution Status: Consent Agenda
File created: 6/27/2023 In control: Transportation
On agenda: 7/11/2023 Final action:
Title: Adoption of Resolution Retroactively Increasing the Director of Transportation's Change Order Authority to a Total of $149,701 for Department of Transportation Contract Number 210017 for Construction of the 2019 Storm Damage Repairs on Mountain View Road, County Road 510, Milepost 20.00 (Boonville Area)
Attachments: 1. Resolution 23-132, 2. Resolution, 3. Letter

 

To:  Board of Supervisors

FromTransportation

Meeting DateJuly 11, 2023

 

Department Contact:  

Howard N. Dashiell

Phone: 

707-463-4363

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Adoption of Resolution Retroactively Increasing the Director of Transportation’s Change Order Authority to a Total of $149,701 for Department of Transportation Contract Number 210017 for Construction of the 2019 Storm Damage Repairs on Mountain View Road, County Road 510, Milepost 20.00 (Boonville Area)

End

 

Recommended Action/Motion:

recommendation

Adopt Resolution retroactively increasing the Director of Transportation’s change order authority to a total of $149,701 for Department of Transportation Contract Number 210017 for construction of the 2019 storm damage repairs on Mountain View Road, County Road 510, milepost 20.00 (Boonville Area); and authorize Chair to sign the same.

End

 

Previous Board/Board Committee Actions:

By Resolution Number (No.) 21-045 (April 6, 2021), the Board of Supervisors authorized the Director of Transportation to advertise for bids for Department of Transportation (DOT) Contract No. 210017 and to award the contract to the lowest responsive, responsible bidder.                     

 

Summary of Request

On September 12, 2022, DOT awarded DOT Contract No. 210017 to Bouthillier’s Construction, Inc., of Willits, California, in the amount of $239,035 for construction of the 2019 Storm Damage Repairs on Mountain View Road, County Road 510, Milepost 20.00, which was $142,165 under the Engineer’s Estimate. Pursuant to Resolution No. 07-008, the Director’s change order authority was $23,904 per contract change order. Over the course of construction, additional Rock Slope Protection (RSP) was required to properly repair the storm damage, exceeding the Director’s original contract change order authority by $125,797.  In order to avoid delaying the project and incurring additional costs, the contractor was allowed to proceed with construction and the project was completed on June 12, 2023.  DOT is requesting a retroactive increase of the Director’s change order limits to a total of $149,701 to cover the cost of the additional RSP. DOT will seek reimbursement from the FHWA ER program, and 88.53% of the additional costs are anticipated to be reimbursed.

 

Alternative Action/Motion:

Do not approve increasing change order authority and let the items go to claims.                     

 

Does This Item Support the General Plan? Yes

 

Strategic Plan Priority Designation: A Prepared and Resilient County

 

Supervisorial District:  District 5

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

Fiscal Details:

source of funding: FHWA ER, Road Fund

budgeted in current f/y: Yes

current f/y cost: BU 3030: $17,171 (11.47% local match of CCO)

if no, please describe:

annual recurring cost: N/A

revenue agreement: N/A

 budget clarification: N/A

Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Steve Dunnicliff, Deputy CEO

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Senior Deputy Clerk

Final Status: Adopted

Date: July 11, 2023

Executed Item Type: Resolution   Number: 23-132