Title: Approval of Retroactive Agreement with Mendocino County Fire Safe Council for Ignition Resistant Phase 2 Project Management Services in the Amount of $20,000 for the Term of August 25, 2022 through June 30, 2023
Attachments: 1. Agreement 23-059

 

To:  Board of Supervisors

FromExecutive Office

Meeting DateApril 25, 2023

 

Department Contact:  

Darcie Antle

Phone: 

707-463-4441

Department Contact:  

Xuyen Mallela

Phone: 

707-463-4441

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Approval of Retroactive Agreement with Mendocino County Fire Safe Council for Ignition Resistant Phase 2 Project Management Services in the Amount of $20,000 for the Term of August 25, 2022 through June 30, 2023

End

 

Recommended Action/Motion:

recommendation

Approve retroactive agreement with Mendocino County Fire Safe Council for Ignition Resistant project management services in the amount of $20,000 for the term of August 25, 2022 through June 30, 2023; and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

Board approved agreement with Mendocino County Fire Safe Council for Ignition Resistant Phase 1 Project Management Services on May 4, 2021.                     

 

Summary of Request

The Ignition-Resistant Project (Project) is a rebate program intended to incentivize homeowners to replace flammable roofing materials with non-flammable materials to improve community resiliency in the face of wildfire and prevent loss of life and property.

 

 

The County receives funding for this project through FEMA’s Hazard Mitigation Grant Program (HMGP). The project is completed in two phases, with Phase 1 is completed. This contract is for Mendocino County Fire Safe Council (MCFSC) to manage the beginning of Phase 2 of the Project.  County staff will manage the remaining portion of Phase 2.

 

This contract is retroactive to allow the contractor to immediately begin work after Phase 2 was approved, in order to complete the project on time.

 

 

Alternative Action/Motion:

Return to staff for alternative handling.                     

 

Supervisorial District:  All

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: n/a

 

Fiscal Details:

source of funding: FEMA Hazard Mitigation Grant Program (HMGP)

budgeted in current f/y: Yes

current f/y cost: $20,000

if no, please describe: n/a

annual recurring cost: N/A

revenue agreement: No

 

budget clarification: Disaster Recovery 2910

 Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Executive Office

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Senior Deputy Clerk

Final Status: Approved

Date: April 25, 2023