Title: Discussion and Possible Action Regarding Presentation from Aircon Energy Regarding Energy and Sustainability Services for County-Owned Facilities, Including Results of an Initial Feasibility Study (Sponsor: Executive Office)
Attachments: 1. Presentation, 2. Preliminary Assessment Report -Mendocino County_04.12.17 (3), 3. Preliminary Assessment EEM Table - Mendocino County 03152017, 4. Mendocino Cash Flow Traditional Loan CEC 1%

 

To:  Board of Supervisors

FromExecutive Office

Meeting DateFebruary 26, 2019

 

Department Contact:  

Carmel J. Angelo

Phone: 

463-4441

Department Contact:  

Steve Dunnicliff

Phone: 

463-4441

 

Item Type:   Regular Agenda

 

Time Allocated for Item: 60 min

 

 

Agenda Title:

title

Discussion and Possible Action Regarding Presentation from Aircon Energy Regarding Energy and Sustainability Services for County-Owned Facilities, Including Results of an Initial Feasibility Study

(Sponsor: Executive Office)

End

 

Recommended Action/Motion:

recommendation

Receive the presentation, including the results of an initial feasibility study from Aircon Energy, and provide direction that may include having Aircon Energy conduct a formal investment grade audit of County facilities and return to the Board to present final recommendations and options to implement and fund energy efficiency improvements.

End

 

Previous Board/Board Committee Actions:

On January 2, 2002, the Board approved an agreement with Aircon Energy for energy retrofit services for the Public Health facility on Dora Street.  On September 20, 2016 the Board received a presentation from Aircon Energy and directed staff work with the firm to complete a feasibility study.  In budget planning for FY 18-19, there was Board discussion regarding the exploration of solar at County facilities.                      

 

Summary of Request

Aircon Energy, serving northern California since 1974, specializes in turnkey energy and sustainability project identification, development and implementation for state and local governments.  Projects range from identifying and implementing solutions to reduce energy and water costs, such as interior/exterior lighting and controls to water usage and irrigation.  The premise behind project identification is to determine what facility renewal measures are applicable and will generate a proportionate amount of savings that basically make the project cost neutral, such as alternative energy solutions (solar), control systems and/or sustainable materials and operations.  As the County’s facilities continue to age and maintenance costs rise, staff have been proactive in readily identifying and implementing measures to reduce utility costs by installing LED lighting and drought tolerant landscaping where possible.  Building envelope improvements, control systems, and heating, air-conditioning and ventilation (HVAC) technologies have vastly improved since 2003, the last time Aircon Energy completed a project for the County.  Aircon Energy can assist staff and/or offer turnkey projects that are self-funded or financed long-term in order to take advantage of new technologies and solutions while lowering operating costs and prolonging the life of the facility and equipment.

 

Alternative Action/Motion:

Direct staff to conduct further research on energy and sustainability companies and bring forth recommendations.                     

 

Supervisorial District:  All

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: <www.airconenergy.com>

 

Fiscal Details:

source of funding: N/A

budgeted in current f/y: N/A

current f/y cost: N/A

if no, please describe:

annual recurring cost: N/A

revenue agreement: N/A

 

 budget clarification: No monetary cost associated with Aircon Energy proceeding to complete an investment grade audit; there would be indirect costs associated with staff time.  However, Aircon’s completion of this audit will identify projects for Aircon to complete with a cost, estimated from the feasibility study, to be in excess of $5.285 million.  Preliminary information indicates completed projects would generate energy and maintenance savings with a combined payback period estimated at 12 years; these improvements would likely be funded by low interest loans.

Agreement/Resolution/Ordinance Approved by County Counsel: N/A

 

CEO Liaison: Janelle Rau, Deputy CEO

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

FOR COB USE ONLY

Executed By: Meribeth Dermond, Deputy Clerk II

Final Status:Approved with Direction

Date: February 27, 2019

  IT IS ORDERED that the Board of Supervisors Receive the presentation, including the results of an initial feasibility study from Aircon Energy, and provide direction that may include having Aircon Energy conduct a formal investment grade audit of County facilities and return to the Board to present final recommendations and options to implement and fund energy efficiency improvements;