Legislation Details

File #: 26-0537    Version: 1 Name:
Type: Agreement Status: Consent Agenda
File created: 5/18/2026 In control: Executive Office
On agenda: 6/2/2026 Final action:
Title: Approval of Appropriation Request in the Amount of $200,000 Increasing the Juvenile Hall Backup Generator and Fencing Project Budget from $409,223 to $609,223; Approval of the Juvenile Hall Backup Generator and Fencing Project Plans and Specifications; and Authorization to Award to and Approval of an Agreement with Ferranti Construction, Incorporated in the Amount of $523,632 for the Juvenile Hall Backup Generator and Fencing Project at 585 Low Gap Road, Ukiah for a Period of Two Hundred Seventy (270) Calendar Days from the Date of Issuance of the Notice to Proceed
Attachments: 1. Agreement 26-055, 2. Appropriation Form - Signed, 3. Bid Results Juvenile Hall Generator Project

To:  BOARD OF SUPERVISORS

From:  Executive Office and Probation

Meeting Date:  June 2, 2026

 

Department Contact:  

Doug Anderson

Phone: 

707-234-6054

Department Contact:  

Izen Locatelli

Phone: 

707-234-6911

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Approval of Appropriation Request in the Amount of $200,000 Increasing the Juvenile Hall Backup Generator and Fencing Project Budget from $409,223 to $609,223; Approval of the Juvenile Hall Backup Generator and Fencing Project Plans and Specifications; and Authorization to Award to and Approval of an Agreement with Ferranti Construction, Incorporated in the Amount of $523,632 for the Juvenile Hall Backup Generator and Fencing Project at 585 Low Gap Road, Ukiah for a Period of Two Hundred Seventy (270) Calendar Days from the Date of Issuance of the Notice to Proceed

End

 

Recommended Action/Motion:

recommendation

Approve the appropriation request in the amount of $200,000 increasing the Juvenile Hall Backup Generator and Fencing Project budget from $409,223 to $609,223; approve the Juvenile Hall Backup Generator and Fencing Project plans and specifications; authorize award to and approval of an Agreement with Ferranti Construction, Incorporated in the amount of $523,632 for the Juvenile Hall Backup Generator Project at 585 Low Gap Road, Ukiah, for the period of two hundred seventy (270) calendar days from the date of issuance of the Notice to Proceed; and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

At the June 25, 2024, meeting, the Board approved the Fiscal Year 2024-25 budget, including approval and appropriation for the Juvenile Hall Backup Generator Project in the amount of $369,223 and the Juvenile Hall Fencing project in the amount of $40,000. At the December 17, 2024 meeting, the Board approved the design and engineering agreement for the project with Yao Engineering in the amount of $56,825.                     

 

Summary of Request

The majority of the Mendocino County Juvenile Hall facility currently lacks backup power, creating operational and safety concerns during utility outages. The Juvenile Hall Backup Generator and Fencing Project will provide for the installation of a new emergency backup generator system to supply power to the facility’s main electrical service panel to support the continued operation of critical building systems during power interruptions and provide long needed improvements to the perimeter fencing for the facility.

 

On May 23, 2026, three bids were received for the Juvenile Hall Backup Generator and Fencing project with Ferranti Construction’s bid being by far the lowest bid. While the second low bidder submitted a protest letter citing a subcontractor listing error, staff, including the County Counsel’s office, found that the bid irregularity met the intent of the legislation and did not offer the bidder an advantage. The protesting bidder has elected not to appeal staff’s determination.

 

Several factors were found to have increased project costs since the project was created in 2024. Cost escalation for major manufactured products like generators over the two years since then have continued to rise; additional security measures were requested in developing the fencing scope including an automatic gate operator and security camera modifications; and numerous underground utilities were found to be present at the generator location, requiring specialized excavation.

 

With the likelihood that delays needed to re-bid the project could further increase the cost, staff recommends approval of the appropriation and award. 

 

Alternative Action/Motion:

Do not authorize the award and provide direction to staff.                     

 

Strategic Plan Priority Designation: A Safe and Healthy County

 

Supervisorial District:  District 2

                                          

Vote Requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

 

Fiscal Details:

source of funding: JPA Growth Funds from realignment fund LLERA 11

current f/y cost: Less than $50,000

budget clarification: Encumbered funds will be carried forward into FY 26-27.

annual recurring cost: None

budgeted in current f/y (if no, please describe): Yes

revenue agreement: No

AGREEMENT/RESOLUTION/ORDINANCE APPROVED BY COUNTY COUNSEL: Yes

CEO Liaison: Darcie Antle, CEO                                                               

CEO Review: Yes                                            

CEO Comments:

 