File #: 24-0939    Version: 1 Name:
Type: Approval Status: Consent Agenda
File created: 10/7/2024 In control: General Services Agency
On agenda: 10/22/2024 Final action:
Title: Approval of Agreement (Second Amendment to Professional Services Agreement) with Sally Swanson Architecture and Planning, Incorporated in the Amount of $4,000 for Architectural Services for the Mill Creek Park Restroom Project on Mill Creek Road in Talmage for a Total Contract Amount of $53,775
Attachments: 1. Agreement 24-180
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

To:  BOARD OF SUPERVISORS

From:  General Services Agency

Meeting Date:  October 22, 2024

 

Department Contact:  

Tim Hallman

Phone: 

707-234-6050

Department Contact:  

Doug Anderson

Phone: 

707-264-6050

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Approval of Agreement (Second Amendment to Professional Services Agreement) with Sally Swanson Architecture and Planning, Incorporated in the Amount of $4,000 for Architectural Services for the Mill Creek Park Restroom Project on Mill Creek Road in Talmage for a Total Contract Amount of $53,775

End

 

Recommended Action/Motion:

recommendation

Approve Agreement (second amendment to professional services Agreement) with Sally Swanson Architecture and Planning, Incorporated in the amount of $4,000 for architectural services for the Mill Creek Park Restroom Project on Mill Creek Road in Talmage for a Total Contract Amount of $53,775; and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

On February 8, 2022, the Board of Supervisors adopted resolution 22-031 which approved filing of an application for a Per Capita Grant with the State Department of Parks and Recreation for the installation of permanent restrooms at Mill Creek Park.                     

 

Summary of Request

On July 31, 2023, the General Services Agency Director approved agreement GS-5767 with Sally Swanson Architecture and Planning, Incorporated (SSA) for architectural services for the development of project plans and specifications to install permanent vault restrooms at Mill Creek Park in the amount of $40,000. A previous amendment to provide surveying services for the project increased the contract amount to $49,775. Subsequent evaluation of the proposed design required relocation of one of the restroom sites and additional services by SSA in the amount of $4,000. The resulting total contract amount exceeds the contract authority of the Purchasing agent, requiring approval by the Board of Supervisors for this amendment to the contract.

 

Alternative Action/Motion:

Do not approve the Amendment and provide direction to staff.                     

 

Strategic Plan Priority Designation: A Safe and Healthy County

 

Supervisorial District:  All

                                          

Vote Requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

Fiscal Details:

source of funding: CA 1713

current f/y cost: $4,000

budget clarification: Project costs are funded by the Per Capita Grant in the amount of $400,000 and County general fund match previously appropriated in the amount of $96,892 

annual recurring cost: N/A

budgeted in current f/y (if no, please describe): Yes

revenue agreement: No

AGREEMENT/RESOLUTION/ORDINANCE APPROVED BY COUNTY COUNSEL: Yes

CEO Liaison: Tony Rakes, Acting Deputy CEO                                                               

CEO Review: Yes                                            

CEO Comments:

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Senior Deputy Clerk

Final Status: Approved

Date: October 22, 2024

Executed Item Type: Agreement

 

Number: 24-180