Title: Authorization for the Facilities and Fleet Division Manager to Establish a Capital Improvement Project to Complete Emergency Water Damage Remediation and Repairs at South Yokayo Center, 747 South State Street, Ukiah CA in the Amount of $30,000; and Authorization for the Facilities and Fleet Division Manager to Act as Project Manager to Enter Contracts and Approve Change Orders for the Projects, Pursuant to Public Contract Code Section 20142

 

To:  Board of Supervisors

FromGeneral Services 

Meeting DateDecember 6, 2022

 

Department Contact:  

Janelle Rau

Phone: 

707-234-6050

Department Contact:  

Dan Mazzanti

Phone: 

707-234-6050

Department Contact:  

Doug Anderson

Phone: 

707-234-6050

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Authorization for the Facilities and Fleet Division Manager to Establish a Capital Improvement Project to Complete Emergency Water Damage Remediation and Repairs at South Yokayo Center, 747 South State Street, Ukiah CA in the Amount of $30,000; and Authorization for the Facilities and Fleet Division Manager to Act as Project Manager to Enter Contracts and Approve Change Orders for the Projects, Pursuant to Public Contract Code Section 20142

End

 

Recommended Action/Motion:

recommendation

Authorize the Facilities and Fleet Division Manager to establish a Capital Improvement project to complete emergency water damage remediation and repairs at South Yokayo Center, 747 S. State Street, Ukiah CA in the Amount of $30,000; and authorize the Facilities and Fleet Division Manager to act as project manager to enter contracts and approve change orders for the project, pursuant to Public Contract Code section 20142.

End

 

Previous Board/Board Committee Actions:

Approval of the 22-23 budget including carry forward funding for the Capital Improvement Budget Unit 1710 for Unanticipated Capital Projects.

 

Summary of Request

On October 17, 2022, Social Services reported flooding in the South Yokayo restrooms which resulted in damaged flooring and wall systems in the area near the restrooms. Staff resolved the plumbing issue and with the assistance of a remediation contractor completed drying and water damage remediation to prevent microbial growth. Staff continues work required to complete repairs to the water damage area at a total cost not to exceed $30,000. It is anticipated that all related costs are reimbursable through an Insurance claim or fund.

 

Alternative Action/Motion:

Provide direction to staff.                     

 

Does This Item Support the General Plan? Yes

 

Supervisorial District:  District 2

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

Fiscal Details:

source of funding: BU 1710

budgeted in current f/y: Yes

current f/y cost: $30,000

if no, please describe:

annual recurring cost: None

revenue agreement: No

 budget clarification: Funding for this project will be from previously approved funding for unanticipated  capital projects in the CI/1710 budget, with reimbursement from insurance and or Social Services.

Agreement/Resolution/Ordinance Approved by County Counsel: N/A

 

CEO Liaison: Executive Office

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Senior Deputy Clerk

Final Status: Approved