File #: 23-0300    Version: 1 Name:
Type: Approval Status: Consent Agenda
File created: 2/27/2023 In control: General Services Agency
On agenda: 3/14/2023 Final action:
Title: Authorization for the Facilities and Fleet Division Manager to Establish a Capital Improvement Project to Complete the Agriculture Building Roof Replacement at 890 N. Bush Street, Ukiah in the Amount of $300,000 and Authorization for the Facilities and Fleet Division Manager to Act as Project Manager to Enter Contracts and Approve Change Orders for the Projects, Pursuant to Public Contract Code Section 20142; and Approval of Appropriation of Project Funds from the 2022 Certificate of Participation (COP) Bond Financing
Attachments: 1. Appropriation Form - Signed

 

To:  Board of Supervisors

FromGeneral Services 

Meeting DateMarch 14, 2023

 

Department Contact:  

Janelle Rau

Phone: 

707-234-6050

Department Contact:  

Doug Anderson

Phone: 

707-234-6050

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Authorization for the Facilities and Fleet Division Manager to Establish a Capital Improvement Project to Complete the Agriculture Building Roof Replacement at 890 N. Bush Street, Ukiah in the Amount of $300,000 and Authorization for the Facilities and Fleet Division Manager to Act as Project Manager to Enter Contracts and Approve Change Orders for the Projects, Pursuant to Public Contract Code Section 20142; and Approval of Appropriation of Project Funds from the 2022 Certificate of Participation (COP) Bond Financing

End

 

Recommended Action/Motion:

recommendation

Authorize the Facilities and Fleet Division Manager to establish a Capital Improvement project to complete the Agriculture Building Roof Replacement at 890 N. Bush Street, Ukiah in the amount of $300,000 and authorize the Facilities and Fleet Division Manager to act as Project Manager to enter contracts and approve change orders for the project, pursuant to Public Contract Code section 20142; approve appropriation of project funds from the 2022 COP Bond Financing; and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

Approval of the 2022 Certificate of Participation Bond Financing application which included the Agriculture Building Roof as a named project. During the January 24, 2023, meeting, the Board of Supervisors received a status update on Bond Financing estimates and priorities and during the February 28, 2023, meeting, provided direction to staff to appropriate funding for the full amount of the project.                     

 

Summary of Request

For several years, the Facilities and Fleet Division of the General Services Agency has identified the Agriculture Building Roof replacement as a priority project for funding at the quarterly budget update meetings, and last year the Board included this project in the COP Bond Financing application. As the primary impetus for seeking the COP financing was to ensure that the SB 844 Jail Expansion project was fully funded, the prudent direction from the board was to defer funding discretionary projects until after the Jail bids were received and final funding requirements confirmed. Last month’s winter storm event revealed roof leaks not previously identified and raised the urgency level of this project to critical. This item creates the Capital Improvement project and appropriates the funding as directed by the Board of Supervisors at the February 28th meeting.

 

Alternative Action/Motion:

Provide direction to staff.                     

 

Does This Item Support the General Plan? Yes

 

Supervisorial District:  District 2

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

Fiscal Details:

source of funding: BU 1710

budgeted in current f/y: No

current f/y cost: $20,000

if no, please describe: Appropriation included

annual recurring cost: N/A

revenue agreement: No

 budget clarification: Funding for this project will be from the 2022 COP Bond financing funds in the  amount of $360,000 and expended over the current and next fiscal years.

Agreement/Resolution/Ordinance Approved by County Counsel: N/A

 

CEO Liaison: Executive Office

 

 

CEO Review: Choose an item. 

 

 

CEO Comments:

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Senior Deputy Clerk

Final Status: Approved

Date: March 14, 2023