To: Board of Supervisors
From: Transportation
Meeting Date: September 12, 2017
|
Department Contact: |
Howard N. Dashiell |
Phone: |
463-4363 |
|
Item Type: Consent Agenda |
|
Time Allocated for Item: N/A |
Agenda Title:
title
Adoption of Resolution Authorizing Department of Transportation to Award an Amount Greater Than Previously Authorized; Previously Authorized Estimate of $193,000, Increased to $247,459, Department of Transportation Contract Number 160089 to Construct the Hearst Willits Road Culvert Replacement (Willits Area)
End
Recommended Action/Motion:
recommendation
Adopt Resolution authorizing Department of Transportation to award an amount greater than previously authorized; previously Authorized estimate of $193,000, increased to $247,459, Department of Transportation contract no. 160089 to construct the Hearst Willits Road Culvert Replacement (Willits Area); and authorize Chair to sign same.
End
Previous Board/Board Committee Actions:
By Resolution 17-048 (April 4, 2017) the Board authorized the Director of Transportation to advertise for bids and award DOT Contract No. 160089 in the estimated amount of $193,000 for the Hearst Willits Road Culvert Replacement.
Summary of Request:
DOT has prepared construction plans, specifications, estimates, and contract documents for DOT Contract No. 160089, Hearst Willits Road Culvert Replacement. This project includes replacement of existing undersized culverts corroded to the point of needing replacement with a larger precast concrete box culvert. This project was advertised for bids on August 6, 2017. The bid opening was on August 21, 2017, to which two sealed bids were received. All bids came in higher than the previously authorized estimate of $193,000, with the lowest responsive bidder being Wylatti Resource Management, Inc., with a bid of $247,459. Funds for this project are currently available from the Road Fund. DOT requests and recommends the Board authorize the Director of Transportation to award, for an amount greater than previously authorized, DOT Contract No. 160089 to Wylatti Resource Management, Inc., in the amount of $247,459, for the Hearst Willits Road Culvert Replacement.
Alternative Action/Motion:
Postpone awarding of contract and delay commencement of construction.
Supplemental Information Available Online at: N/A
Fiscal Impact:
|
Source of Funding: Budget Unit 3010 |
Budgeted in Current F/Y: Yes |
|
|
Current F/Y Cost: : $247,459 |
Annual Recurring Cost: N/A |
|
|
|
|
|
|
Supervisorial District: District 3 |
Vote Requirement: Majority |
|
Agreement/Resolution/Ordinance Approved by County Counsel: Yes
|
CEO Liaison: Janelle Rau, Deputy CEO |
|
|
|
CEO Review: Yes |
|
|
CEO Comments:

FOR COB USE ONLY
|
Executed By: Nicole French |
Final Status:Approved |
|
Date: September 15, 2017 |
Executed Item Number: Resolution 17-134 |
|
Note to Department: |
|
|
|
|