Legislation Details

File #: 23-0034    Version: 1 Name:
Type: Approval Status: Consent Agenda
File created: 1/9/2023 In control: Information Services
On agenda: 1/24/2023 Final action:
Title: Approval of Sixth Amendment to Agreement 15-056 with Thomson Reuters/Aumentum in the Amount of $250,000, for a New Total Contract Amount of $2,914,533, Related to the Acquisition of County-Wide Property Tax Software System, Authorizing the Addition of Professional Consulting Services and Travel
Attachments: 1. Agreement 15-056-A6

 

To:  Board of Supervisors

FromInformation Technology

Meeting DateJanuary 24, 2023

 

Department Contact:  

Steve Dunnicliff

Phone: 

463-4411

Department Contact:  

Tony Rakes

Phone: 

234-6000

Department Contact:  

Chamise Cubbison

Phone: 

234-6860

Department Contact:  

Katrina Bartlomie

Phone: 

234-6822

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Approval of Sixth Amendment to Agreement 15-056 with Thomson Reuters/Aumentum in the Amount of $250,000, for a New Total Contract Amount of $2,914,533, Related to the Acquisition of County-Wide Property Tax Software System, Authorizing the Addition of Professional Consulting Services and Travel

End

 

Recommended Action/Motion:

recommendation

Approve sixth amendment to agreement 15-056 with Thomson Reuters/Aumentum in the amount of $250,000, for a new total contract amount of $2,914,533, related to the acquisition of county-wide property tax software system, authorizing the addition of professional consulting services and travel; authorize the Chief Executive Officer or their designee to execute any and all documents in relation to the transaction; and authorize the Chief Executive Officer or their designee to sign any future amendments to the Agreement that do not alter the fiscal aspect of the Thomson Reuters/Aumentum master agreement for licensed software, hardware, and services; and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

In June 2013, the Board of Supervisors adopted a five-year Capital Improvement Plan (CIP) which included the replacement of the County’s property tax software system. On June 9, 2015, the Board of Supervisors approve the master agreement with Thomson Reuters/Aumentum. in the amount of $1,701,429 for the acquisition of county-wide property tax software system. The Board of Supervisors subsequently approved five amendments between March 2017 and May 2022 totaling $963, 104.

 

Summary of Request

In 2013, the County initiated the Request for Proposal (RFP) for replacement of the county-wide property tax software system due to being obsolete and represented a significant risk of catastrophic failure. In June 2015, the Board approved the agreement with Thomson Reuters/Aumentum for the acquisition of county-wide property tax system in the amount of $1,701,429. Project implementation was postponed due to many factors including delays with County of Riverside’s implementation.

 

The County-Wide Property Tax Software System initial Go-Live was implemented in February 2021 and the project team continued with post go-live activities. Information Technology has been assisting the stakeholders and vendor in resolving discrepancies resulting from the initial data conversion that caused balancing issues that have prevented some of the standard processes to function correctly.

 

In 2021, the County re-negotiated the Aumentum contract to include a large final acceptance payment. Thirty-four items were originally identified as requiring closure on the final acceptance list. This includes important items such as conversation balancing, AB8/RDA factors, and Supplementals, Corrections, and Escapes.

 

A need for additional LOA hours to work through challenges associated with configuration assistance, process and tools support, production data entry, and system optimization has been identified. It is requested that the Board of Supervisors approve the sixth amendment to agreement 15-056 with Thomson Reuters/Aumentum in the amount of $250,000 for the addition of professional consulting services and travel.

 

Alternative Action/Motion:

Do not approve amendment and provide alternate direction to staff.                     

 

Does This Item Support the General Plan? N/A

 

Strategic Plan Priority Designation: An Effective County Government

 

Supervisorial District:  All

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

Fiscal Details:

source of funding: IT Reserve, BU 0717

budgeted in current f/y: Yes

current f/y cost: $495,830

if no, please describe:

annual recurring cost: Varies (Estimated annual support identified in master agreement /yr.)

revenue agreement: N/A

budget clarification: Current F/Y cost is an estimate only based on available project funds. Project costs are allocated in the IT Reserve funds. Ongoing maintenance identified in the master agreement is budgeted at the department level annually through the County budget process.

Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Executive Office

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Senior Deputy Clerk

Final Status:Approved

Date: January 24, 2023

Executed Item Type: Agreement   Number: 15-056-A6