File #: 24-0367    Version: 1 Name:
Type: Approval Status: Consent Agenda
File created: 3/22/2024 In control: Transportation
On agenda: 4/9/2024 Final action:
Title: Adoption of Resolution Approving Notice of Completion and Release of Contract Surety and Authorizing the Director of Transportation to Accept the Contract for Department of Transportation Contract Number 210021 for the Seismic Retrofit Project on Eureka Hill Road over Garcia River, County Road 505, Milepost 4.92 (Point Arena Area)
Attachments: 1. Resolution 24-051, 2. Resolution, 3. Inspection Memo, 4. Notice of Completion
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

To:  BOARD OF SUPERVISORS

From:  Transportation

Meeting Date:  April 9, 2024

 

Department Contact:  

Howard Dashiell

Phone: 

707-463-4363

Department Contact:  

Alicia Winokur

Phone: 

707-463-4363

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Adoption of Resolution Approving Notice of Completion and Release of Contract Surety and Authorizing the Director of Transportation to Accept the Contract for Department of Transportation Contract Number 210021 for the Seismic Retrofit Project on Eureka Hill Road over Garcia River, County Road 505, Milepost 4.92 (Point Arena Area)

End

 

Recommended Action/Motion:

recommendation

Adopt Resolution approving the Notice of Completion and Release of Contract Surety and authorizing the Director of Transportation to accept the contract for Department of Transportation Contract Number 210021 for the Seismic Retrofit Project on Eureka Hill Road over Garcia River, County Road 505, milepost 4.92 (Point Arena Area); and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

By Resolution Number (No.) 08-205 (October 21, 2008), the Board of Supervisors (BOS) approved BOS Agreement No. 08-185/ Department of Transportation (DOT) Agreement No. 080059, with Mark Thomas and Company for the plans, specifications, and estimate bid package for the seismic retrofit of two County maintained bridges, the Eureka Hill Road Bridge over Garcia River, County Road (CR) 505, milepost (MP) 4.92, and the Moore Street Bridge over Russian River, CR 229B, MP 0.45. By Resolution No. 18-203 (December 18, 2018), the BOS approved BOS Agreement No. 18-178/DOT Agreement No. 180027, with Mark Thomas and Company to complete the plans, specifications, and estimate bid package for the seismic retrofit of the Eureka Hill Road Bridge over Garcia River. By Resolution No. 21-04 (April 6, 2021), the Board authorized the Director of Transportation to advertise for bids and award DOT Contract No. 210021 for construction of the Seismic Retrofit Project on Eureka Hill Road over Garcia River. By Resolution No. 23-129 (July 11, 2023), the Board approved Contract Change Order No. 3, increasing the contract amount by $1,044,237.08 for a total contract amount of $2,540,899.55.                     

 

Summary of Request

Construction has been completed. DOT would like to file the Notice of Completion to commence the applicable lien periods, and pending no claims, release Contract Sureties after expiration of lien periods. Contract surety must be released as prescribed by existing laws. DOT is also requesting the authority for the Director of Transportation to accept DOT Contract No. 210021 at a later date for the purpose of grant funding claims.

 

Alternative Action/Motion:

Postpone approval of the Notice of Completion and release of Contract Sureties for DOT Contract No. 210021.                     

 

Strategic Plan Priority Designation: A Prepared and Resilient County

 

Supervisorial District:  District 5

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

Fiscal Details:

source of funding: N/A

 

current f/y cost: N/A

 

annual recurring cost: N/A

 

budgeted in current f/y: N/A

if no, please describe:

revenue agreement: N/A

AGREEMENT/RESOLUTION/ORDINANCE APPROVED BY COUNTY COUNSEL: Yes

CEO Liaison: Steve Dunnicliff, Deputy CEO                                                               

CEO Review: Yes                                            

CEO Comments:

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Senior Deputy Clerk

Final Status: Adopted

Date: April 9, 2024

Executed Item Type: Resolution

 

Number: 24-051