File #: 25-0431    Version: 1 Name:
Type: Resolution Status: Consent Agenda
File created: 4/30/2025 In control: Transportation
On agenda: 5/20/2025 Final action:
Title: Adoption of Resolution Authorizing Department of Transportation to Advertise for Bids and Award Two Department of Transportation Contracts to Construct the 2023 Highway Safety Improvement Program Projects: Guardrail Upgrades and Systemic Roadway Segment Improvements, at an Estimated Cost of $1,200,000 (Countywide)
Attachments: 1. Resolution 25-090, 2. Resolution, 3. HSIP Letter
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

To:  BOARD OF SUPERVISORS

From:  Transportation

Meeting Date:  May 20, 2025

 

Department Contact:  

Howard N. Dashiell

Phone: 

707-463-4363

Department Contact:  

Alicia Winokur

Phone: 

707-463-4363

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Adoption of Resolution Authorizing Department of Transportation to Advertise for Bids and Award Two Department of Transportation Contracts to Construct the 2023 Highway Safety Improvement Program Projects: Guardrail Upgrades and Systemic Roadway Segment Improvements, at an Estimated Cost of $1,200,000 (Countywide)

End

 

Recommended Action/Motion:

recommendation

Adopt Resolution authorizing Department of Transportation to advertise for bids and award two Department of Transportation contracts to construct the 2023 Highway Safety Improvement Program projects: guardrail upgrades and systemic roadway segment improvements, at an estimated cost of $1,200,000 (Countywide); and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

None.                     

 

Summary of Request

These two Department of Transportation (DOT) contracts will provide for construction of the 2023 Highway Safety Improvement Program (HSIP) projects on various County roads, at an estimated cost of $1,200,000 (~$900,000 for guardrail upgrades and ~$300,000 for systemic roadway segment improvements). Funding for Fiscal Years (FY) 2024-25 and 2025-26 is budgeted through Budget Unit (BU) 3041 and is anticipated to be 90% reimbursable through the Federal Highway Administration (FHWA), with the local match funded with road funds. The Project includes upgrading existing guardrails and end treatments at areas with a high probability of vehicles unintentionally exiting the roadway. Upgrades will occur along East Side Potter Valley Road at mile post (MP) 6.00 and 6.21, Point Cabrillo Drive, at MP 2.65 and 2.85, Babcock Lane, at MP 0.10, Primrose Drive at MP 1.60, and Comptche-Ukiah Road at MP 7.30. The project also includes the installation/upgrade of signs with new fluorescent sheeting (regulatory or warning) and the installation of chevron signs on horizontal curves, delineators, reflectors, and/or object markers along Branscomb Road, Eastside Calpella Road, North State Street, Sherwood Road, Comptche Ukiah Road, Simpson Lane, Vichy Springs Road, Valley Road, South State Street, Mountain View Road, Pudding Creek Road, Eel River Road, and Henderson Lane.

 

Alternative Action/Motion:

Postpone advertising for bids and award of contracts and delay commencement of construction.                     

 

Strategic Plan Priority Designation: A Prepared and Resilient County

 

Supervisorial District:  All

                                          

Vote Requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

 

Fiscal Details:

source of funding: FHWA HSIP, BU 3041

current f/y cost: $45,000 estimated local share

budget clarification: N/A

annual recurring cost: N/A

budgeted in current f/y: Yes

if no, please describe: estimated FY 25/26 local share: $75,000 revenue agreement: No

AGREEMENT/RESOLUTION/ORDINANCE APPROVED BY COUNTY COUNSEL: Yes

CEO Liaison: Steve Dunnicliff, Deputy CEO                                                               

CEO Review: Yes                                            

CEO Comments:

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Senior Deputy Clerk

Final Status: Adopted

Date: May 20, 2025

Executed Item Type: Resolution

 

Number: 25-090