File #: 17-1064    Version: 1 Name:
Type: Resolution Status: Adopted
File created: 11/7/2017 In control: Transportation
On agenda: 12/5/2017 Final action:
Title: Adoption of Resolution Increasing Change Order Authority in the Amount of $25,593 to a Total of $50,741 and Approving Notice of Completion and Release of Contract Surety for Department of Transportation Contract Number 160047, 2016 Laytonville Landfill Cap Repair (Laytonville Area)
Sponsors: Transportation
Attachments: 1. Resolution 17-187, 2. Letter - DOT Contract No. 160047, 3. Inspection Memo - DOT Contract No. 160047, 4. Unsigned NOC - DOT Contract No. 160047

 

To:  Board of Supervisors

FromTransportation

Meeting DateDecember 5, 2017

 

Department Contact:  

Howard N. Dashiell

Phone: 

463-4363

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Adoption of Resolution Increasing Change Order Authority in the Amount of $25,593 to a Total of $50,741 and Approving Notice of Completion and Release of Contract Surety for Department of Transportation Contract Number 160047, 2016 Laytonville Landfill Cap Repair (Laytonville Area)

End

 

Recommended Action/Motion:

recommendation

Adopt Resolution increasing change order authority in the amount of $25,593 to a total of $50,741 and approving Notice of Completion and release of Contract Surety for Department of Transportation (DOT) Contract Number (No.) 160047, 2016 Laytonville Landfill Cap Repair (Laytonville Area); and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

By Resolution No. 16-099 (August 2, 2016) the Board of Supervisors (BOS) authorized DOT to advertise for bids and award DOT Contract No. 160047 to perform repairs to a portion of the westerly capping fill of the closed Laytonville landfill, and increase the Director of Transportation’s change order authority to 10% of the contract.                     

 

Summary of Request

On September 7, 2016, DOT Contract No. 160047 was awarded to Bouthillier’s Construction, Inc., of Willits, California, in the amount of $251,480.  A 10% contingency was authorized for this project.  Construction on this project has been completed. The total amount of contract change orders exceed the current change order limit of $25,148 by $25,593, so DOT requests the BOS increase the limit by $25,593 to $50,741.  These overages are due to adjustments in the estimated quantities of line items, which were not known at the time of construction and were necessary to complete the work without causing project delays.  Bouthillier Construction, Inc., has agreed to accept a lower unit price for the items exceeding 125 percent of the originally estimated quantities.  Funds are available in the Landfill Closure Fund to cover this increase, which has not yet been paid to the contractor.  Additionally, DOT would like to file the Notice of Completion to commence the applicable lien periods, and pending no claims, release Contract Sureties after expiration of lien periods.  Contract Surety must be released as prescribed by existing laws.

 

Alternative Action/Motion:

Do not approve the requested increase in change order authority and postpone approval of the Notice of Completion and release of Contract Sureties for DOT Contract No. 160047.                     

 

Supplemental Information Available Online at: N/A

 

 

Fiscal Impact:

Source of Funding: Budget Unit 4511 Landfill Closure Fund

Budgeted in Current F/Y: Yes

 

Current F/Y Cost: $25,593

Annual Recurring Cost: N/A

 

 

 

 

Supervisorial District:  District 3

Vote Requirement:  Majority

 

Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Steve Dunnicliff, Deputy CEO

 

 

CEO Review: Yes 

 

 

CEO Comments:

FOR COB USE ONLY

Executed By: Nadia Tipton

Final Status:Adopted

Date: December 6, 2017

Executed Item No.: Resolution Number: 17-187

Note to Department: 

 

Executed Documents Returned to Department: Originals  _____  Copies  _____   Hand Delivered   ___  Interoffice Mail  ___ Executed Agreement Sent to Auditor?  Y/N