Title: Approval of Change Order Number 01 to Agreement 24-211 with FRC, a California Corporation for the Agriculture - Farm Advisor Front Entry Repair Project for Additional Work Required to Replace the Column Footings and Additional Plaster in the Amount of $20,926.19 for a New Agreement Total of $217,926.19 and Extend the Contract Term to May 30, 2025
Attachments: 1. Agreement 24-211-A1
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: BOARD OF SUPERVISORS
FROM: Executive Office
MEETING DATE: May 20, 2025


DEPARTMENT CONTACT:
Doug Anderson
PHONE:
707-234-6054


ITEM TYPE: Consent Agenda

TIME ALLOCATED FOR ITEM: N/A


AGENDA TITLE:
title
Approval of Change Order Number 01 to Agreement 24-211 with FRC, a California Corporation for the Agriculture - Farm Advisor Front Entry Repair Project for Additional Work Required to Replace the Column Footings and Additional Plaster in the Amount of $20,926.19 for a New Agreement Total of $217,926.19 and Extend the Contract Term to May 30, 2025
End

RECOMMENDED ACTION/MOTION:
recommendation
Approve Change Order number 01 to Agreement 24-211 with FRC, a California corporation for agriculture, Farm Advisor Front Entry Repair project, for additional work required to replace the column footings and additional plaster, in the amount of $20,926.19, for a new Agreement total of $217,926.19, and to extend the contract term to May 30, 2025; and authorize Chair to sign same.
End

PREVIOUS BOARD/BOARD COMMITTEE ACTIONS:
On April 9, 2024, the Board of Supervisors authorized the establishment of the Capital Improvement project to repair the Entry Fa?ade for the Agriculture - Farm Advisor Building in the amount of $200,000. On December 17, 2025 the Board authorized the award of the repair contract to FRC, Inc. in the amount of $197,000 and increased the project budget to $250,000.

SUMMARY OF REQUEST:
Last year damage to one of the columns supporting the entry at the Agriculture - Farm Advisor building exposed extensive rot damage, further investigation revealed rot damage to all four of the columns. Staff provided for temporary shoring to support the structure while repairs could be designed and completed. After structural investigation, the project design included new structural columns and beams supported on the existing column footings and replacing the architectural features in kind. After the contractor had removed the plaster and damaged c...