To: Board of Supervisors
From: Executive Office
Meeting Date: May 5, 2020
Department Contact: |
Steve Dunnicliff |
Phone: |
463-4441 |
Department Contact: |
Doug Anderson |
Phone: |
234-6054 |
Item Type: Consent Agenda |
|
Time Allocated for Item: N/A |
Agenda Title:
title
Authorization to Award a Contract to Fort Bragg Electric, Inc. in the Amount of $249,926 for the Sheriff’s Office Underground Fiber Project at 951 Low Gap Road, Ukiah, CA, Effective May 5, 2020 through November 25, 2020, and Authorization for the Facilities and Fleet Division Manager to Act as Project Manager to Approve Change Orders for the Project, Pursuant to Public Contract Code Section 20142
End
Recommended Action/Motion:
recommendation
Authorize contract award to Fort Bragg Electric in the amount of $249,926 for the Sheriff’s Office Underground Fiber Project, effective May 5, 2020 through November 25, 2020, and authorize Chair to sign same, further authorize the Facilities and Fleet Division Manager to act as Project Manager to enter contracts and approve change orders for the project, pursuant to Public Contract Code section 20142.
End
Previous Board/Board Committee Actions:
Approval of the 2019-2020 Budget including allocation IT Reserve funding for IT Master Plan Projects including at the Sheriff’s Office; Authorization for Establishing a Capital Improvement Project for Structured Cabling for the Sheriff’s Office with funding from the IT Reserve on August 20, 2019.
Summary of Request:
Sheriff’s Office Structured Cabling and Underground Fiber Project was created in the Capital Improvement 1710 Budget Unit to complete the IT Master Plan Project previously approved as part of that budget unit. Plans were developed and bids were first received for this project on October 29, 2019. At that time all bids exceeded the available funding. The project was re-bid on March 12, 2020 removing the interior cabling. The Information Services and Facilities and Fleet Divisions of the Executive Office recommend award to the low bidder, Fort Bragg Electric in the amount of $249,926 for the Underground Fiber Optic Cabling to the Sheriff’s Office.
Alternative Action/Motion:
Reject all bids and provide direction to staff.
Supervisorial District: District 2
vote requirement: Majority
Supplemental Information Available Online At: N/A
Fiscal Details:
source of funding: BU 1710 |
budgeted in current f/y: Yes |
current f/y cost: $249,926 |
if no, please describe: |
annual recurring cost: N/A |
revenue agreement: No |
budget clarification: The project was created with funding from IT Reserve in the amount of $223,250. The balance of funding will be provided from the IT Reserve funding for IT Master Plan Project for the 2019-20 Fiscal Year. |
Agreement/Resolution/Ordinance Approved by County Counsel: Yes
CEO Liaison: Executive Office |
|
|
CEO Review: Yes |
|
|
CEO Comments:
FOR COB USE ONLY
Executed By: Lindsey Dunham, Senior Deputy Clerk |
Final Status:Approved |
Date: May 5, 2020 |
Executed Item Number: Agreement Number: 20-062 |
Note to Department Number of Original Agreements Returned to Dept: 0 Original Agreement Delivered to Auditor? No |
|
|
|