File #: 20-0490    Version: 1 Name:
Type: Resolution-Agreement Status: Consent Agenda
File created: 5/28/2020 In control: Transportation
On agenda: 6/23/2020 Final action:
Title: Adoption of Resolution Approving Department of Transportation Agreement Number 200035, Professional Services Agreement with SHN Consulting Engineers & Geologists, in the Amount of $57,225 for Construction Management Services for the Term Starting Upon Execution of the Agreement Through December 31, 2021, and Authorizing an Additional Contingency Amount of $6,000 for the Williams Creek Bridge Replacement on Powerhouse Road, County Road 248A (Potter Valley Area)
Sponsors: Transportation
Attachments: 1. Letter, 2. Resolution 20-084, 3. Resolution, 4. Agreement 20-096

 

To:  Board of Supervisors

FromTransportation

Meeting DateJune 23, 2020

 

Department Contact:  

Howard N. Dashiell

Phone: 

463-4363

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Adoption of Resolution Approving Department of Transportation Agreement Number 200035, Professional Services Agreement with SHN Consulting Engineers & Geologists, in the Amount of $57,225 for Construction Management Services for the Term Starting Upon Execution of the Agreement Through December 31, 2021, and Authorizing an Additional Contingency Amount of $6,000 for the Williams Creek Bridge Replacement on Powerhouse Road, County Road 248A (Potter Valley Area)End

 

Recommended Action/Motion:

recommendation

Adopt Resolution approving Department of Transportation Agreement Number 200035, Professional Services Agreement with SHN Consulting Engineers & Geologists, in the amount of $57,225 for construction management services for the term starting upon execution of the Agreement through December 31, 2021, and authorizing an additional contingency amount of $6,000 for the Williams Creek Bridge Replacement on Powerhouse Road, County Road 248A, (Potter Valley Area); and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

By Resolution Number (No.) 15-093 (June 16, 2015), the Board of Supervisors (BOS) approved Department of Transportation (DOT) Agreement No. 140022  with MGE Engineering, Inc., for plans, specifications, and estimate bid package for the Williams Creek Bridge on Powerhouse Road. By Resolution No. 20-004 (January 7, 2020), the Board authorized the Director of Transportation to advertise for bids and award DOT Contract No. 190033 for construction of the Williams Creek Bridge Replacement project. By Resolution No. 20-045 (April 20, 2020), the Board authorized the Director of Transportation to close Powerhouse Road at Williams Creek for construction of the Williams Creek Bridge Replacement project                     

 

Summary of Request

There is a need for construction management services for the construction phase of the project.  DOT has insufficient engineering staff to perform the work in a timely manner and therefore requires professional, expert, and technical services of a temporary nature.  DOT has undergone a qualification based selection process to find a consultant who can perform the construction management work and has selected SHN Consulting Engineers & Geologists (SHN), based on their qualifications.  DOT Agreement No. 200035 provides for specialized consultant services with SHN for construction management of the Williams Creek Bridge Replacement Project in the amount of $57,225.  Costs of the project are to be funded primarily through the Federal Highway Administration (FHWA) Highway Bridge Program (HBP), with the local match covered by the Toll Credit Program. DOT also believes it is prudent to request a contingency in the amount of $6,000 in order to facilitate timely completion of the work.

 

Alternative Action/Motion:

Postpone award of DOT Agreement No. 200035.                     

 

Supervisorial District:  District 1

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

Fiscal Details:

source of funding: FHWA HBP, Budget Unit 3041

budgeted in current f/y: Yes

current f/y cost: $6,000 (Estimated)

if no, please describe:

annual recurring cost: $0

revenue agreement: N/A

 budget clarification: N/A

 Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Steve Dunnicliff, Deputy CEO

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Staff Assistant II

Final Status:Adopted

Date: June 25, 2020

Executed Item: Resolution   Number: 20-084 and Executed Item: Agreement   Number: 20-096

Note to Department Number of Original Agreements Returned to Dept: 3 Original Agreement Delivered to Auditor? Yes