Title: Authorization for the Facilities and Fleet Division Manager to Establish a Capital Improvement Project to Complete Sewer Repairs at Jail Building 2 in the Amount of $7,500 and Authorization for the Facilities and Fleet Division Manager to Act as Project Manager to Enter Contracts and Approve Change Orders for the Project, Pursuant to Public Contract Code Section 20142

 

To:  Board of Supervisors

FromExecutive Office

Meeting DateJuly 14, 2020

 

Department Contact:  

Steve Dunnicliff

Phone: 

463-4441

Department Contact:  

Doug Anderson

Phone: 

234-6054

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

Agenda Title:

title

Authorization for the Facilities and Fleet Division Manager to Establish a Capital Improvement Project to Complete Sewer Repairs at Jail Building 2 in the Amount of $7,500 and Authorization for the Facilities and Fleet Division Manager to Act as Project Manager to Enter Contracts and Approve Change Orders for the Project, Pursuant to Public Contract Code Section 20142

End

 

Recommended Action/Motion:

recommendation

Authorize the Facilities and Fleet Division Manager to establish a Capital Improvement project to complete sewer repairs at Jail Building 2 in the amount of $7,500 and authorize the Facilities and Fleet Division Manager to act as Project Manager to enter contracts and approve change orders for the project, pursuant to Public Contract Code section 20142.

End

 

Previous Board/Board Committee Actions:

Approval of the 2019-2020 Budget including allocation of $100,000 for the Capital Improvement Budget Unit 1710 for Unanticipated Capital Projects including First Quarter Budget Adjustments on November 19, 2019.                     

 

Summary of Request

As reported in the June 9 CEO Report, a clogged sewer line was identified in the County Jail Building 2 on June 1.  The technician responding to the service call found the line obstructed with bedding or clothing and was not able to clear with drain auger equipment. Ultimately, emergency repairs were required, and a contractor was hired to precisely locate the blockage, remove the slab, dig up the sewer line, cut out the pipe to remove the blockage, repair the pipe and refinish.

 

Alternative Action/Motion:

Provide direction to staff.                     

 

Supervisorial District:  District 2

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

Fiscal Details:

source of funding: BU 1710

budgeted in current f/y: Yes

current f/y cost: $7,500

if no, please describe:

annual recurring cost: N/A

revenue agreement: No

 budget clarification: Fiscal Year 2020 Budget Unit 1710 Capital Improvement line item for unanticipated capital projects was funded with $100,000 

 Agreement/Resolution/Ordinance Approved by County Counsel: N/A

 

CEO Liaison: Executive Office

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Deputy Clerk I

Final Status:Approved

Date: July 17, 2020