To: Board of Supervisors
From: Executive Office
Meeting Date: January 26, 2021
Department Contact: |
Janelle Rau |
Phone: |
463-4441 |
Department Contact: |
Doug Anderson |
Phone: |
234-6054 |
Item Type: Consent Agenda |
|
Time Allocated for Item: N/A |
Agenda Title:
title
Authorization for the Facilities and Fleet Division Manager to Establish a Capital Improvement Project to Complete the Removal and Replacement of the Uninterrupted Power Supply for the Server Room in the Courthouse Annex in the amount of $20,000 and Authorization for the Facilities and Fleet Division Manager to Act as Project Manager to Enter Contracts and Approve Change Orders for the Project, Pursuant to Public Contract Code Section 20142
End
Recommended Action/Motion:
recommendation
Authorize the Facilities and Fleet Division Manager to establish a Capital Improvement project to complete the removal and replacement of the Uninterrupted Power Supply (UPS) for the Server Room in the Courthouse Annex in the amount of $20,000 and authorize the Facilities and Fleet Division Manager to act as Project Manager to enter contracts and approve change orders for the project, pursuant to Public Contract Code section 20142.
End
Previous Board/Board Committee Actions:
Approval of the 2020-2021 Budget including Information Services funding for new equipment.
Summary of Request:
The Information Services Budget for 2021 fiscal year included funding to replace the UPS for the servers located in the Courthouse Annex. The equipment budget installation of the UPS will be transferred to Capital Improvement budget unit to complete this public project as required.
Alternative Action/Motion:
Provide direction to staff.
Supervisorial District: District 2
vote requirement: Majority
Supplemental Information Available Online At:
Fiscal Details:
source of funding: BU 1960 |
budgeted in current f/y: Yes |
current f/y cost: $20,000 |
if no, please describe: |
annual recurring cost: N/A |
revenue agreement: No |
|
budget clarification: The installation of the new UPS equipment was budgeted in the IS Budget Unit, Installation will be completed in CI as a public project capital improvement.
Agreement/Resolution/Ordinance Approved by County Counsel: N/A
CEO Liaison: Executive Office |
|
|
CEO Review: Yes |
|
|
CEO Comments:
FOR COB USE ONLY
Executed By: Atlas Pearson, Deputy Clerk I |
Final Status:Approved |
Date: January 27, 2021 |
|
|
|
|
|