Mendocino Logo
File #: 21-0346    Version: 1 Name:
Type: Resolution Status: Consent Agenda
File created: 3/9/2021 In control: Transportation
On agenda: 4/6/2021 Final action:
Title: Adoption of Resolution Approving Notice of Completion and Release of Contract Surety and Authorizing the Director of Transportation to Accept the Contract for Department of Transportation Contract Number 160090 for the Rowes Creek Bridge Replacement on Sherwood Road, County Road 311, Milepost 5.52 (Willits Area)
Attachments: 1. Resolution 21-044, 2. Inspection Memo, 3. Resolution, 4. Notice of Completion

 

To:  Board of Supervisors

FromTransportation

Meeting DateApril 6, 2021

 

Department Contact:  

Howard N. Dashiell

Phone: 

463-4363

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Adoption of Resolution Approving Notice of Completion and Release of Contract Surety and Authorizing the Director of Transportation to Accept the Contract for Department of Transportation Contract Number 160090 for the Rowes Creek Bridge Replacement on Sherwood Road, County Road 311, Milepost 5.52 (Willits Area)

End

 

Recommended Action/Motion:

recommendation

Adopt Resolution approving the Notice of Completion and Release of Contract Surety and authorizing the Director of Transportation to accept the contract for Department of Transportation Contract Number 160090 for the Rowes Creek Bridge Replacement on Sherwood Road, County Road 311, milepost 5.52 (Willits Area); and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

By Resolution Number (No.) 12-079 (May 22, 2012), the Board of Supervisors (BOS) approved Department of Transportation (DOT) Agreement No. 110121  with Quincy Engineering, Inc., for the plans, specifications, and estimate bid package for the Rowes Creek Bridge Replacement on Sherwood Road. By Resolution No. 16-141 (December 6, 2016), the Board authorized the Director of Transportation to advertise for bids and award DOT Contract No. 160090 for construction of the Rowes Creek Bridge Replacement project. By Resolution No. 19-212 (July 16, 2019), the Board increased the Director of Transportation’s change order authority.                     

 

Summary of Request

Construction has been completed. DOT would like to file the Notice of Completion to commence the applicable lien periods, and pending no claims, release Contract Sureties after expiration of lien periods. Contract surety must be released as prescribed by existing laws. DOT is also requesting the authority for the Director of Transportation to accept DOT Contract No. 160090 at a later date for the purpose of grant funding claims.

 

Alternative Action/Motion:

Postpone approval of the Notice of Completion and release of Contract Sureties for DOT Contract No. 160090.                     

 

Supervisorial District:  District 3

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

Fiscal Details:

source of funding: N/A

budgeted in current f/y: N/A

current f/y cost: N/A

if no, please describe:

annual recurring cost: N/A

revenue agreement: N/A

 budget clarification: N/A

 Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Steve Dunnicliff, Deputy CEO

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Deputy Clerk I

Final Status:Adopted

Date: April 6, 2021

Executed Item Type: Resolution   Number: 21-044