Mendocino Logo
File #: 21-0474    Version: 1 Name:
Type: Resolution-Agreement Status: Consent Agenda
File created: 4/9/2021 In control: Transportation
On agenda: 5/4/2021 Final action:
Title: Adoption of Resolution Approving Department of Transportation Agreement Number 200041, with Wood Rodgers, Inc., in the Amount of $762,353, for Professional Engineering Design Services, and Authorizing an Additional Contingency Amount of $76,300, for the Outlet Creek Bridge Replacement on Reynolds Highway, County Road 310, Milepost 4.87 (Willits Area)
Attachments: 1. Agreement 21-085, 2. Resolution 21-063, 3. Letter, 4. Resolution

 

To:  Board of Supervisors

FromTransportation

Meeting DateMay 4, 2021

 

Department Contact:  

Howard N. Dashiell

Phone: 

463-4363

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Adoption of Resolution Approving Department of Transportation Agreement Number 200041, with Wood Rodgers, Inc., in the Amount of $762,353, for Professional Engineering Design Services, and Authorizing an Additional Contingency Amount of $76,300, for the Outlet Creek Bridge Replacement on Reynolds Highway, County Road 310, Milepost 4.87 (Willits Area)

End

 

Recommended Action/Motion:

recommendation

Adopt Resolution approving Department of Transportation Agreement Number 200041, with Wood Rodgers, Inc., in the amount of $762,353, for professional engineering design services and authorizing an additional contingency amount of $76,300, for the Outlet Creek Bridge Replacement on Reynolds Highway, County Road 310, Milepost 4.87 (Willits Area); and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

None.                     

 

Summary of Request

Department of Transportation (DOT) Agreement Number (No.) 200041 provides for preliminary engineering and design work, including environmental studies, plans, specifications, and estimate, needed for the Outlet Creek Bridge Replacement on Reynolds Highway.  Wood Rodgers has agreed to perform the required work for a not-to-exceed amount of $762,353.  Costs of the project are to be funded primarily through the Federal Highway Administration (FHWA) Highway Bridge Program (HBP), with the local match covered through Toll Credits.  Future amendments for additional work will be determined based on supplemental funding from FHWA.  DOT believes it is prudent to begin work with the existing funds from FHWA Allocation No. 1 in the amount of $446,300, followed by Allocation No. 2, in the amount of $316,053 upon receiving confirmation of the additional grant funding.  DOT also believes it would be expedient to request a 10% contingency in the amount of $76,300, in order to facilitate timely completion of the work.

 

Alternative Action/Motion:

Postpone approval of DOT Agreement No. 200041                     

 

Supervisorial District:  District 3

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

Fiscal Details:

source of funding: FHWA HBP, Budget Unit 3041

budgeted in current f/y: Yes

current f/y cost: $45,000 (Estimated)

if no, please describe:

annual recurring cost: N/A

revenue agreement: Yes

 budget clarification: N/A

 Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Steve Dunnicliff, Deputy CEO

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Deputy Clerk I

Final Status:Adopted

Date: May 6, 2021

Executed Item Type: Resolution   Number: 21-063 Executed Item Type: Agreement   Number: 21-085

Note to Department Number of Original Agreements Returned to Dept: 2 Original Agreement Delivered to Auditor? Yes