To: Board of Supervisors
From: Executive Office
Meeting Date: December 19, 2017
Department Contact: |
Carmel J. Angelo |
Phone: |
463-4441 |
Department Contact: |
Steve Dunnicliff |
Phone: |
463-4441 |
Department Contact: |
Doug Anderson |
Phone: |
234-6054 |
Item Type: Consent Agenda |
|
Time Allocated for Item: N/A |
Agenda Title:
title
Authorization to Award a Contract to Swithenbank Construction, Inc., in the Amount of $235,736 for the Little River Airport Terminal Building Remodel Project Located at 43001 Little River Airport Road, Little River, California; and Authorization for the Facilities and Fleet Division Manager to Act as Project Manager and Approve Change Orders for the Project, Pursuant to Public Contract Code Section 20142
End
Recommended Action/Motion:
recommendation
Authorize contract award to Swithenbank Construction, Inc., in the amount of $235,736 for the Litter River Airport Terminal Building Remodel Project; authorize the Facilities and Fleet Division Manager to act as Project Manager and approve change orders for the project pursuant to Public Contract Code section 20142; and authorize chair to sign same.
End
Previous Board/Board Committee Actions:
Approval of 2017-2018 fiscal year budget that included funding for the Little River Airport Terminal Remodel Project in Budget Unit 1710 Capital Improvements.
Summary of Request:
The existing Terminal Building is a gateway for numerous visitors to the Mendocino Coast is outdated and all interior and exterior finishes are worn out. The project will gut the building and provide a fully updated and remodeled facility within the same footprint of the existing terminal. The work includes upgraded electrical, plumbing and mechanical systems, a new roof and a reconfigured manager’s office and waiting area, new exterior siding, new paint throughout and ADA improvements to meet current standards. The bid price exceeded the project budget; however, funding allocations within the Capital Improvement Budget for County wide painting, roofing and mechanical upgrades are available to supplement the project budget. The Executive Office, Facilities and Fleet Division, recommends approval of contract award to Swithenbank Construction, Inc., in the amount of $235,736.
Alternative Action/Motion:
Reject bid(s) and provide staff with further direction.
Supplemental Information Available Online at: N/A
Fiscal Impact:
Source of Funding: Budget Unit 1710 - CI 820 |
Budgeted in Current F/Y: Yes |
|
Current F/Y Cost: $235,736 |
Annual Recurring Cost: None |
|
|
|
|
Supervisorial District: District 5 |
Vote Requirement: Majority |
|
Agreement/Resolution/Ordinance Approved by County Counsel: Yes
CEO Liaison: Janelle Rau, Deputy CEO |
|
|
CEO Review: Yes |
|
|
CEO Comments:
FOR COB USE ONLY
Executed By: Nadia Tipton |
Final Status:Approved |
Date: December 20, 2017 |
Executed Item No.: Agreement Number: 17-152 |
Note to Department: |
|
Executed Documents Returned to Department: Originals 5 Copies _____ Hand Delivered 3 Interoffice Mail ___ Executed Agreement Sent to Auditor? Y |
|