Title: Discussion and Possible Action Including Adoption of Resolution Authorizing Department of Transportation to Advertise for Bids and Award Department of Transportation Contract Number 180010 to Perform a 2018 Asphalt Concrete Maintenance Project on Various County Maintained Roads (Redwood Valley, Calpella, Ukiah, and Hopland Areas) (Sponsor: Transportation)
Sponsors: Transportation
Attachments: 1. Resolution 18-062, 2. Director Letter
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

To:  Board of Supervisors

FromTransportation

Meeting DateApril 24, 2018

 

Department Contact:  

Howard N. Dashiell

Phone: 

463-4363

 

Item Type:   Regular Agenda

 

Time Allocated for Item: 5 minutes

 

 

Agenda Title:

title

Discussion and Possible Action Including Adoption of Resolution Authorizing Department of Transportation  to Advertise for Bids and Award Department of Transportation Contract Number 180010 to Perform a 2018 Asphalt Concrete Maintenance Project on Various County Maintained Roads (Redwood Valley, Calpella, Ukiah, and Hopland Areas)

(Sponsor: Transportation)

End

 

Recommended Action/Motion:

recommendation

Adopt Resolution authorizing Department of Transportation (DOT) to advertise for bids and award DOT Contract Number (No.) 180010 to perform a 2018 Asphalt Concrete (AC) Maintenance Project on various County Maintained Roads (Redwood Valley, Calpella, Ukiah, and Hopland Areas); and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

None.                       

 

Summary of Request

DOT will prepare and administer construction plans, specifications, estimates and contract documents for Contract No. 180010, 2018 AC Maintenance Project on various County Maintained Roads.  This project will be to preserve 7.58 miles of road surfaces within the Mendocino County Maintained Road System, at an estimated average cost of $263,697.00 per mile when completed.  The roads are Central Avenue, County Road (CR) 229, from milepost (MP) 0.00 to MP 0.91, Eastside Calpella Road, CR 227, from MP 0.00 to MP 3.75, and University Road, CR 116B, from MP 0.00 to MP 2.91.

 

Alternative Action/Motion:

Postpone the needed pavement preservation.                     

 

Supplemental Information Available Online at: N/A

 

 

Fiscal Impact:

Source of Funding: Road Funds-Budget Unit 3041 $1 million - Cannabis or other general funds $1 million - Road Maintenance Funds, including Road Maintenance and Rehabilitation Account funds

Budgeted in Current F/Y: Yes

 

Current F/Y Cost: $2.0 million (Estimated)

Annual Recurring Cost: N/A

 

 

 

 

Supervisorial District:  District 1 & 5

Vote Requirement:  Majority

 

Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Steve Dunnicliff, Deputy CEO

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

 

 

 

FOR COB USE ONLY

Executed By: Willetta Callaghan

Final Status:Adopted

Date: April 27, 2018

Executed Item No.: Resolution Number: 18-062

Note to Department: 

 

Executed Documents Returned to Department: N/A Originals  _____  Copies  _____   Hand Delivered   ___  Interoffice Mail  ___ Executed Agreement Sent to Auditor? N