Title: Adoption of Resolution Approving Amendment Number 3 to Board of Supervisors Agreement Number 12-079/Department of Transportation Agreement Number 110123, with Willdan Engineering in the Amount of $64,762, for Additional Professional Engineering Design Services for the Term Starting Upon Execution of the Agreement and Continuing through December 31, 2021, and Authorizing an Additional Contingency Amount of $41,000, for the Mattole River Bridge Replacement on Briceland Road, County Road 435, Milepost 0.63 (Whale Gulch Area)
Sponsors: Transportation
Attachments: 1. Resolution 18-184, 2. Agreement 12-079-A1, 3. Letter

 

To:  Board of Supervisors

FromTransportation

Meeting DateDecember 4, 2018

 

Department Contact:  

Howard N. Dashiell

Phone: 

463-4363

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Adoption of Resolution Approving Amendment Number 3 to Board of Supervisors Agreement Number 12-079/Department of Transportation Agreement Number 110123, with Willdan Engineering in the Amount of $64,762,  for Additional Professional Engineering Design Services for the Term Starting Upon Execution of the Agreement and Continuing through December 31, 2021, and Authorizing an Additional Contingency Amount of $41,000, for the Mattole River Bridge Replacement on Briceland Road, County Road 435, Milepost 0.63 (Whale Gulch Area)

End

 

Recommended Action/Motion:

recommendation

Adopt Resolution approving Amendment Number 3 to Board of Supervisors Agreement Number 12-079/Department of Transportation Agreement Number 110123, with Willdan Engineering (Willdan) in the amount of $64,762, for additional professional engineering design services for the term starting upon execution of the agreement and continuing through December 31, 2021, and authorizing an additional contingency amount of $41,000, for the Mattole River Bridge Replacement on Briceland Road, County Road 435, Milepost 0.63 (Whale Gulch Area); and authorize the Chair to sign same.

End

 

Previous Board/Board Committee Actions:

By Resolution Number (No.) 12-098, July 10, 2012, Board of Supervisors (BOS) authorized Department of Transportation (DOT) to enter into BOS Agreement No. 12-079/DOT Agreement No. 110123 with Willdan to design the replacement of the Mattole River Bridge on Briceland Road.                     

 

Summary of Request

Amendment No. 3 provides for $64,762 in additional funds needed to complete California Environmental Quality Act/ National Environmental Policy Act documentation, permit applications, the Environmental Commitments Record, Geotechnical Services, finishing the remaining cultural resource documents, and preparing a Water Quality technical memo and Visual Impact Analysis as required by the California Department of Transportation. The costs of replacement of this bridge are anticipated to be paid for by the Federal Highway Bridge Program (FHWA HBP) and Toll Credits.

 

Alternative Action/Motion:

Postpone approval of Amendment No. 3 to BOS Agreement No. 12-079/DOT Agreement No. 110123.                     

 

Supplemental Information Available Online at: N/A

 

 

Fiscal Impact:

Source of Funding: FHWAHB, Budget Unit 3041

Budgeted in Current F/Y: Yes

 

Current F/Y Cost: : $64,762 ($41,000 contingency if needed)

Annual Recurring Cost: N/A

 

 

 

 

Supervisorial District:  District 4

Vote Requirement:  Majority

 

Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Steve Dunnicliff, Deputy CEO

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

 

 

FOR COB USE ONLY

Executed By: Meribeth Dermond

Final Status:Adopted

Date: December 5, 2018

Executed Item Number: Resolution   Item Number: 18-184

 

Final Status:Approved

 

Executed Item Number: Agreement   Item Number:12-079-A1

Note to Department Number of Original Agreements Returned to Dept: Two Original Agreement Delivered to Auditor? Yes