Mendocino Logo
File #: 19-0283    Version: 1 Name:
Type: Approval Status: Approved
File created: 3/21/2019 In control: Executive Office
On agenda: 4/16/2019 Final action:
Title: Authorization to Award a Contract in the Amount of $880,000 to Cupples & Sons Construction, Inc., for the Yokayo Center Exterior Repairs and Accessibility Compliance Project and Authorization for the Chair to Sign the Agreement Upon Receipt of the Bidder's Required Bonds and Certificates of Insurance; and Authorization of the Facilities and Fleet Division Manager to Act as Project Manager and Approve Change Orders for the Project, Pursuant to Public Contract Code Section 20142
Attachments: 1. Agreement 19-123

 

To:  Board of Supervisors

FromExecutive Office

Meeting DateApril 16, 2019

 

Department Contact:  

Steve Dunnicliff

Phone: 

463-4441

Department Contact:  

Doug Anderson

Phone: 

234-6054

 

 

 

 

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Authorization to Award a Contract in the Amount of $880,000 to Cupples & Sons Construction, Inc., for the Yokayo Center Exterior Repairs and Accessibility Compliance Project and Authorization for the Chair to Sign the Agreement Upon Receipt of the Bidder’s Required Bonds and Certificates of Insurance; and Authorization of the Facilities and Fleet Division Manager to Act as Project Manager and Approve Change Orders for the Project, Pursuant to Public Contract Code Section 20142

End

 

Recommended Action/Motion:

recommendation

Approve contract award in the amount of $880,000 to Cupples & Sons Construction, Inc., for the Yokayo Center Exterior Repairs and Accessibility Compliance Project at the Yokayo Center, 737 and 747 South State Street in Ukiah; and authorize the Chair to sign Agreement upon receipt of the bidder’s required bonds and certificates of insurance; and authorize the Facilities and Fleet Division Manager to act as project manager and approve change orders for the project, pursuant to Public Contract Code section 20142.

End

 

Previous Board/Board Committee Actions:

Approval of 2018-19 fiscal year budget that includes funding for the Repair and Replace Front Canopy at Yokayo Center Project in the amount of $60,000 and the mid-year budget adjustment that includes an additional $860,000 allocation for this project.  Board approval of an agreement, contingent on receipt of required bonds and insurance, is an approach that is periodically taken to expedite construction projects. 

                     

Summary of Request

The discovery of a hazardous condition last year in which the cement plaster ceiling of the entry canopies and covered walkway was in danger of falling resulted in the closure of the walkways under the canopy and the emergency removal of the ceilings at the County owned building entries at the Yokayo Center, subsequently Project was established for the removal and replacement of the entry façade for the Yokayo Center. Project plans and specifications for the Yokayo Center Exterior Repairs and Accessibility Compliance Project were issued for bid on March 8, 2019, in accordance with the Uniform Public Construction Cost Accounting, Alternative Procedures for public projects and bids were opened on April 3rd, 2019. The Executive Office, Facilities and Fleet Division staff have reviewed the bids and determined that Cupples Construction is the lowest responsive and responsible bidder with a bid of $880,000. The bid price will require funding to be allocated through the budget process into FY 19-20.  The Executive Office, Facilities and Fleet Division recommends approval of contract award to Cupples & Sons Construction, Inc., and authorization for the Board Chair to sign the agreement in the amount of  $880,000 for the Yokayo Center Exterior Repairs and Accessibility Compliance Project, contingent upon receipt of the required bonds and certificates of insurance, as determined by the Facility & Fleet Manager. 

 

Alternative Action/Motion:

Reject all bids and provide staff further direction.

                     

Supervisorial District:  All

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: n/a

 

Fiscal Details:

source of funding: BU 1710; CI 866

budgeted in current f/y: Yes

current f/y cost: Estimated at $550,000

if no, please describe:

annual recurring cost: N/A

revenue agreement: No

 

budget clarification: The funding allocated to this project includes design costs in addition to this construction contract.  The project expense will be paid over two fiscal years, with a balance of approximately $400,000 budgeted and paid in Fiscal Year 19-20.

 Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Steve Dunnicliff, Deputy CEO

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

 

FOR COB USE ONLY

Executed By: Lindsey Dunham, Deputy Clerk

Final Status:Approved

Date: April 17, 2019

Executed Item Number: Agreement   Number: 19-123

Note to Department Number of Original Agreements Returned to Dept: 2 Original Agreement Delivered to Auditor? Yes