File #: 22-0922    Version: 1 Name:
Type: Approval Status: Consent Agenda
File created: 6/27/2022 In control: Public Health
On agenda: 7/12/2022 Final action:
Title: Authorization to Award a Contract to Cupples Construction in the Amount of $900,000 for Phase II of the Homekey Project at 555 S. Orchard St (Ukiah) for the Period of July 12 2022, through January 30, 2023; Authorization for the Public Health Department to Act as Project Manager to Enter Contracts and Approve Change Orders for the Project, Pursuant to Public Contract Code Section 20142; and Authorization for CEO or Her Designee to Negotiate and Enter Into Right of Entry Agreements, Shared Use Agreements, and/or Temporary Construction Easements as May be Necessary for Required Fire Access Modifications
Attachments: 1. Agreement 22-178

 

To:  Board of Supervisors

FromPublic Health 

Meeting DateJuly 12, 2022

 

Department Contact:  

Megan Van Sant

Phone: 

463-7733

Department Contact:  

Steve Dunnicliff

Phone: 

463-4441

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Authorization to Award a Contract to Cupples Construction in the Amount of $900,000 for Phase II of the Homekey Project at 555 S. Orchard St (Ukiah) for the Period of July 12 2022, through January 30, 2023;  Authorization for the Public Health Department to Act as Project Manager to Enter Contracts and Approve Change Orders for the Project, Pursuant to Public Contract Code Section 20142; and Authorization for CEO or Her Designee to Negotiate and Enter Into Right of Entry Agreements, Shared Use Agreements, and/or Temporary Construction Easements as May be Necessary for Required Fire Access Modifications

End

 

Recommended Action/Motion:

recommendation

Authorize award of a contract to Cupples Construction in the amount of $900,000 for Phase II of the Homekey Project at 555 S. Orchard St (Ukiah) for the period of July 12 2022, through January 30, 2023; authorize the Public Health Department to act as Project Manager to enter contracts and approve change orders for the Project, pursuant to Public Contract Code Section 20142; authorize CEO or her designee to negotiate and enter into right of entry agreements, shared use agreements, and/or temporary construction easements as may be necessary for required fire access modifications; and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

The Board has taken many actions in support of the purchase and renovation of a building for Project Homekey (Live Oak Apartments), including action on 8/4/20, 9/22/20, 10/20/20, 1/5/21/, 1/26/21, 2/23/21, 4/20/21, 5/25/21, 8/17/21, 1/25/22 and 4/5/22.                     

 

Summary of Request

The Live Oak Apartments (Project Homekey) are located at 555 S. Orchard Ave, Ukiah.  This building was acquired for use as transitional and permanent housing for individuals and families who are homeless or at risk of becoming homeless.  The State launched this program in part to provide housing for vulnerable populations during the current pandemic.  Conversion of the first 30 units from motel rooms into housing with kitchenettes was completed after having been declared an emergency to meet the State’s initial occupancy expectation.  Phase II is a continuation of that emergency project, and will include installation of kitchenettes in twenty one more rooms, replacement of remaining carpet with vinyl, replacement of the fire alarm system, toilets, improvements to employee workspaces, improvements to the fire lane, and other miscellaneous additions.  A third phase will include construction of a photovoltaic solar system.  The first two building/remodeling bid process for Phase II resulted in the County’s rejection of all bidders.  Following a third competitive process, bids were again received for the construction component of Phase II, with construction bid results as follows:

Kirby Construction                     $959,000

Cupples Construction                     $900,000

Kirby Construction submitted a protest, which was deemed to be without merit by the Purchasing Agent.  As the apparent low bidder, Cupples Construction has received from the County a Notice of Intent to Award a construction contract.  It is recommended the Board approve an agreement with Cupples Construction for completion of Project Homekey Phase II.  A later Third Phase will remain for installation of a photovoltaic solar system on the site.   

 

Alternative Action/Motion:

Provide direction to staff.                     

 

Does This Item Support the General Plan? N/A

 

Strategic Plan Priority Designation: A Safe and Healthy County

 

Supervisorial District:  District 2

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: http://projecthomekeymendocino.org

 

Fiscal Details:

source of funding: CDBG, BU 1714

budgeted in current f/y: Yes

current f/y cost: $900,000

if no, please describe:

annual recurring cost: N/A

revenue agreement: No

 budget clarification: BU 1714 Project Homekey Project Code CF002

Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Executive Office

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Deputy Clerk II

Final Status:Approved

Date: July 13, 2022