Mendocino Logo
File #: 23-0510    Version: 1 Name:
Type: Resolution Status: Consent Agenda
File created: 4/21/2023 In control: Transportation
On agenda: 5/9/2023 Final action:
Title: Adoption of Resolution Authorizing Department of Transportation to Advertise for Bids and Award Three Department of Transportation Contracts to Construct 2023 Storm Damage Permanent Repairs on Mountain View Road, County Road 510, Milepost 1.69, and Mendocino Pass Road, County Road 338, Mileposts 15.50 and 16.75, at an Estimated Cost of $2,110,313 (Countywide)
Attachments: 1. Resolution 23-088, 2. Resolution

 

To:  Board of Supervisors

FromTransportation

Meeting DateMay 9, 2023

 

Department Contact:  

Howard N. Dashiell

Phone: 

707-463-4363

 

 

 

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Adoption of Resolution Authorizing Department of Transportation to Advertise for Bids and Award Three Department of Transportation Contracts to Construct 2023 Storm Damage Permanent Repairs on Mountain View Road, County Road 510, Milepost 1.69, and Mendocino Pass Road, County Road 338, Mileposts 15.50 and 16.75, at an Estimated Cost of $2,110,313 (Countywide)

End

 

Recommended Action/Motion:

recommendation

Adopt resolution authorizing Department of Transportation to advertise for bids and award three Department of Transportation contracts to construct 2023 storm damage permanent repairs on Mountain View Road, County Road 510, milepost 1.65, and Mendocino Pass Road, County Road 338, mileposts 15.50 and 16.75, at an estimated cost of $2,110,313 (Countywide); and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

By Resolution Number (No.) 23-012 (January 10, 2023) the Board of Supervisors declared the existence of a local emergency related to the December 2022/January 2023 Winter Storms Event.                     

 

Summary of Request

These three Department of Transportation (DOT) contracts will provide for construction of the 2023 Storm Damage permanent repairs on Mountain View Road, County Road (CR) 510, milepost (M.P.) 1.69, and Mendocino Pass Road, CR 338, M.P. 15.50 and M.P. 16.75, at an estimated cost of $2,110,313. Funding for Fiscal Year (FY) 2023/24 and FY 2024/25 is budgeted through Budget Unit (BU) 3030, and is anticipated to be 88.53% reimbursable through the Federal Highway Administration (FHWA). The project work will consist of the construction of soldier pile walls, underdrain systems, culverts, etc.  Eligibility for FHWA funding will be confirmed prior to contracting.

 

Alternative Action/Motion:

Postpone advertising for bids and award of contracts and delay commencement of construction.                     

 

Does This Item Support the General Plan? Yes

 

Strategic Plan Priority Designation: A Prepared and Resilient County

 

Supervisorial District:  All

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

Fiscal Details:

source of funding: FHWA, BU 3030

budgeted in current f/y: No

current f/y cost: N/A

if no, please describe: FY 23/24 & 24/25 local share, BU 3030: $242,053 (estimated)

annual recurring cost: N/A

revenue agreement: No

 budget clarification: N/A

Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Steve Dunnicliff, Deputy CEO

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Senior Deputy Clerk

Final Status: Adopted

Date: May 9, 2023

Executed Item Type: Resolution   Number: 23-088