Mendocino Logo
File #: 23-0523    Version: 1 Name:
Type: Approval Status: Consent Agenda
File created: 4/24/2023 In control: Executive Office
On agenda: 5/9/2023 Final action:
Title: Approval of First Amendment to Board of Supervisors Agreement No. 19-239 with Vanir Construction Management Inc. (Vanir) in the Amount of $351,608, for a Total Revised Agreement Amount of $1,861,306 for Services Related to the New Jail Facility, and an Extension of the Contract Term from June 30, 2023 through June 30, 2026
Attachments: 1. Agreement 19-239-A1

 

To:  Board of Supervisors

FromGeneral Services  Executive Office

Meeting DateMay 9, 2023

 

Department Contact:  

Doug Anderson

Phone: 

707-234-6054

Department Contact:  

Steve Dunnicliff

Phone: 

707-463-4441

 

Item Type:   Consent Agenda

 

Time Allocated for Item: N/A

 

 

Agenda Title:

title

Approval of First Amendment to Board of Supervisors Agreement No. 19-239 with Vanir Construction Management Inc. (Vanir) in the Amount of $351,608, for a Total Revised Agreement Amount of $1,861,306 for Services Related to the New Jail Facility, and an Extension of the Contract Term from June 30, 2023 through June 30, 2026

End

 

Recommended Action/Motion:

recommendation

Approve first Amendment to BOS Agreement No. 19-239 with Vanir in the amount of $351,608 for a total revised agreement amount of $1,861,306 for services related to the new jail facility, and an extension of the contract term from June 30, 2023 through June 30, 2026; and authorize Chair to sign same.

End

 

Previous Board/Board Committee Actions:

Approval of agreement BOS 19-239 on October 07, 2019 with Vanir Construction Management Inc. for the SB 844 New Jail Facility in the amount of $1,509,698.  The Board has taken multiple actions related to the new jail facility, most recently on January 10, 2023 when the Board received updates on the project cost estimates and schedule which included costs for design and construction management services associated with project delays.                     

 

Summary of Request

The original contract term was from October 07, 2019 through June 30, 2023. The most recent project schedule shows County occupancy on or after June 30, 2025. The Construction Managers will be responsible to provide services under this contract through occupancy and closeout of the project. The additional time and funding of this amendment will allow their work to continue without interruption through the full project schedule as has been extended due to project delays.

 

Alternative Action/Motion:

Provide direction to staff.                     

 

Does This Item Support the General Plan? N/A

 

Strategic Plan Priority Designation: An Effective County Government

 

Supervisorial District:  All

                                          

vote requirement:  Majority

                                          

 

 

Supplemental Information Available Online At: N/A

 

Fiscal Details:

source of funding: BU 1712

budgeted in current f/y: No

current f/y cost: $351,608

if no, please describe:

annual recurring cost: N/A

revenue agreement: No

budget clarification: Jail project cost estimates provided to the Board in January 2023 and previously have accounted for the escalation in project management costs included here.

Agreement/Resolution/Ordinance Approved by County Counsel: Yes

 

CEO Liaison: Executive Office

 

 

CEO Review: Yes 

 

 

CEO Comments:

 

FOR COB USE ONLY

Executed By: Atlas Pearson, Senior Deputy Clerk

Final Status: Approved

Date: May 9, 2023

Executed Item Type: Agreement   Number: 19-239-A1