File #: 16-1018    Version: 2 Name:
Type: Agreement Status: Approved
File created: 9/19/2016 In control: Executive Office
On agenda: 10/18/2016 Final action: 10/18/2016
Title: Approval of Change Order No. 1 to Board of Supervisors Agreement No. 16-001 with Interactive Resources in the Amount of $23,400 for a Total Revised Agreement Amount of $201,780 for Additional Design and Engineering Services for Roof and HVAC Equipment Replacement Projects for the County Administration Center and the Public Health/Mental Health Buildings
Sponsors: Executive Office
Attachments: 1. Agreement 16-001-A1

TO: Board of Supervisors
FROM: Executive Office
MEETING DATE: October 18, 2016


DEPARTMENT CONTACT:
Christopher Shaver
PHONE:
463-4441


ITEM TYPE: Consent Agenda

TIME ALLOCATED FOR ITEM: N/A


AGENDA TITLE:
title
Approval of Change Order No. 1 to Board of Supervisors Agreement No. 16-001 with Interactive Resources in the Amount of $23,400 for a Total Revised Agreement Amount of $201,780 for Additional Design and Engineering Services for Roof and HVAC Equipment Replacement Projects for the County Administration Center and the Public Health/Mental Health Buildings

End

RECOMMENDED ACTION/MOTION:
recommendation
Approve Change Order No. 1 to Board of Supervisors Agreement No. 16-001 with Interactive Resources in the amount of $23,400 for a total revised Agreement amount of $201,780 for additional design and engineering services for roof and HVAC equipment replacement projects for the County Administration Center and the Public Health/Mental Health buildings; and authorize Chair to sign same
End

PREVIOUS BOARD/BOARD COMMITTEE ACTIONS:
On December 14, 2015, the Board approved agreement BOS 16-001 with Interactive Resources in an amount of $178,380 for design and engineering services for the Capital Improvement roof replacement projects for the Administration Center and the Public Health buildings On August 4, 2015, the Board approved Resolution 15-113 authorizing the Capital Improvement Projects from the FY 2015-2016 recommended budget. On September 9, 2015, the FY 2015-2016 final budget was approved including roof replacement projects for the Administration Center and the Public Health buildings.


SUMMARY OF REQUEST:
Additional engineering and design work to the Administration Center and the Public Health buildings require an additive change order to the original agreement with Interactive Resources. The first phase of the Administration Center regarding design and construction is nearing completion. Design and engineering work continue ...