title
Adoption of Resolution Increasing Change Order Authority in the Amount of $36,104 to a Total of $722,108 for Department of Transportation Contract Number 130078, for Construction of the School Way Bridge Replacement Over the Russian River on School Way, County Road 236 (Redwood Valley Area)
End
RECOMMENDED ACTION/MOTION:
recommendation
Adopt the resolution increasing change order authority in the amount of $36,104 to a total of $722,108 for Department of Transportation ("DOT") Contract Number ("No.") 130078, for construction of the School Way Bridge Replacement over the Russian River on School Way, County Road (CR) 236 (Redwood Valley Area); and authorize Chair to sign same.
End
PREVIOUS BOARD/BOARD COMMITTEE ACTIONS:
By Resolution No. 02-207 (September 17, 2002), the Board of Supervisors ("BOS") approved BOS Agreement No. 02-269/DOT Agreement No. 990106 (Rev 1) with Quincy Engineering, Inc., for plans, specifications and estimate bid packages for replacement of the bridge and approaches on School Way, CR 236, over the Russian River. By Resolution No. 07-008 (January 9, 2007), Board authorized the Director of Transportation to execute changes to any DOT contract that exceeds $250,000 by $25,000, plus 5% of the amount of the original contract costs in excess of $250,000. By Resolution No. 08-139 (August 5, 2008), Board approved Amendment No. 1 for additional scope and restart compensation. By Resolution No. 10-045 (April 6, 2010), Board approved Amendment No. 2 for additional scope of work to incorporate new codes and standards. By Resolution No. 13-073 (July 16, 2013), Board approved Amendment No. 5 for additional engineering and design work. By Resolution No. 14-042 (February 25, 2014), Board approved Amendment No. 6 for a...