File #: 18-2008    Version: 1 Name:
Type: Approval Status: Approved
File created: 8/3/2018 In control: Executive Office
On agenda: 8/21/2018 Final action: 8/21/2018
Title: Authorization for the Facilities and Fleet Division Manager to Establish New Capital Improvement Projects for the Willits Justice Center Police Department ADA Counter Installation (Estimated at $20,000) and the Fort Bragg Justice Center Back-Up Generator Replacement (Estimated at $80,000) with Funding from BU 1710 Budgeted for Approved General Categories and the Admin Center Roof Set-Aside
Attachments: 1. GF APPROVED PROJECTS 19
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Board of Supervisors
FROM: Executive Office
MEETING DATE: August 21, 2018


DEPARTMENT CONTACT:
Doug Anderson
PHONE:
234-6054
DEPARTMENT CONTACT:
Steve Dunnicliff
PHONE:
463-4441


ITEM TYPE: Consent Agenda

TIME ALLOCATED FOR ITEM: N/A


AGENDA TITLE:
title
Authorization for the Facilities and Fleet Division Manager to Establish New Capital Improvement Projects for the Willits Justice Center Police Department ADA Counter Installation (Estimated at $20,000) and the Fort Bragg Justice Center Back-Up Generator Replacement (Estimated at $80,000) with Funding from BU 1710 Budgeted for Approved General Categories and the Admin Center Roof Set-Aside
End

RECOMMENDED ACTION/MOTION:
recommendation
Authorize the Facilities and Fleet Division Manager to establish new capital improvement projects for the Willits Justice Center Police Department ADA counter installation (estimated at $20,000) and the Fort Bragg Justice Center back-up generator replacement (estimated at $80,000) with funding from BU 1710 budgeted for approved general categories and the Admin Center Roof set-aside.
End

PREVIOUS BOARD/BOARD COMMITTEE ACTIONS:
Approval of the 2018-2019 Capital Improvement budget (BU 1710) including allocation of $50,000 for "Unanticipated Capital Projects", $25,000 for "ADA Improvements- Various Locations" and $1.7M for replacement of the Administration Center Roof.

SUMMARY OF REQUEST:
Annual budgeting for Budget Unit 1710 includes allocations for maintenance and upkeep projects that are not known when the budget is created. In recent years these have been divided into general categories for greater clarity. The general categories are:

Unanticipated Capital Projects
$50,000 (approx. $30,000 remaining)
Painting and Exterior Maintenance
$30,000
County-Wide Tree Removal Program
$50,000
Roof Repairs
$100,000
ADA Improvements
$25,000
HVAC Systems Upgrades and Replacement
$100,000 (Approx. $66,000 remaining)

Individual projects are created as ...

Click here for full text